Gasum develops several large-scale biogas plant projects in Sweden

A review of project execution and procurement strategies is underway to enable project activities to resume as quickly and efficiently as possible.

October 30, 2026. Gasum’s main construction partner for the Borlänge plant has been Lundsby Renewable Solutions AB. The company has also been involved in the planning work for the Hörby and Sjöbo plants. On 9 October 2026, Lundsby Renewable Solutions AB filed for bankruptcy.

Gasum is currently working closely with Lundsby’s subcontractors and other relevant stakeholders to minimize the impact on affected projects and secure continued progress. A review of project execution and procurement strategies is underway to enable project activities to resume as quickly and efficiently as possible.

Borlänge: The bankruptcy requires an adjustment to the project schedule. The facility was originally planned to be commissioned in mid-October 2026.

Hörby: The bankruptcy has affected the project’s planned execution schedule. Groundworks that were scheduled to begin in early 2027 will be postponed.

Sjöbo: The project has a legally binding environmental permit and is currently awaiting a final decision on the detailed development plan. At present, Lundsby’s bankruptcy is not expected to affect the overall project schedule.

Gasum remains committed to increasing the availability of renewable biogas and advancing its ongoing investment program in Sweden. The company’s current focus is on securing continued progress in the affected projects, minimizing delays and ensuring that the facilities can be completed and brought into operation as efficiently as possible.